Civil Engineering MCQConstruction MaterialsA construction joint in a concrete slab-on-grade is required if the concrete in the slab cannot be placed in one continuous operation.
A construction joint in a concrete slab-on-grade is required if the concrete in the slab cannot be placed in one continuous operation.